Major Points of Special Project Under SGSY At a Glance
 
 
Project period and action plan
The duration of the project is proposed for a period of three years for the development of leather sector of the Gujarat. through the activities viz. Diagnostic study of working cooperative societies , then empowerment of selected cooperatives of State through Training , Tutoring and mentoring on Technology Up gradation and management , Entrepreneurship development programme , Up gradation of selected potentially viable cooperatives , Up gradation of Leather Articles and Footwear making cooperatives , Arranging buyer sellers meet , Participation in Exhibition within a State ,out side the State and out of the Country also to promote their products and thereby Handsome yields to them , Visit to leather fairs and International leather fairs for market awareness , opening of retail market outlets / showrooms within the country . The above all activities is proposed to implement in the following manner.
 
First year
 
No. Name of activity Duration / Beneficiaries Financial requirement
(In lacs)
Annexure
1. Diagnostic study 3 months 20.00 -
2. Training to Tanners
(Trainers Training)
50 & other remaining 2500 members approx. of 25 cooperative 33.20 A
3. Training to Leather Article and Footwear maker( Trainers training) 25 & other remaining 500 members approx. of 5 cooperative 03.75 B
4. Training for Entrepreneurship Development (EDP) 75 & other remaining 3000 members approx. of 30 cooperatives 03.75 C
5. Upgradation of Tanning Cooperative Societies 5 Tanneries
500 beneficiaries approx.
100.00 D
6. Upgradation of Leather Article & Footwear making cooperative Societies 2 Societies
200 beneficiaries approx.
30.00 E
7. Market Awareness Programme      
  a. Visit to International Leather Fair , Chennai 150 & other remaining 3000 members 30 co op. (approx) 03.33 Table:4.1
  b. Visit to Leather Fair ( either Kolkatta or Delhi ) 150 & other remaining 3000 members 30 co op. (approx 03.33 Table:4.1
8. Project Management , Monitoring & Overhead cost.   8.33  
9. Project Evaluation Cost   8.33  
  Total   214.02